Friday, August 19, 2011

Rainbow Valley


The deck really finishes the back of the house.

Still need a step on this end.

The awkward two story section to the walkout basement is nicely eliminated by the deck.


Tuesday, August 16, 2011

Finishing up the deck.

Final row of decking.

The railing posts are permanent but the railing is temporary.

Final decking.

A rather amazing double rainbow at the end of the day.

Saturday, August 13, 2011

Decking goes down and door cut out.

We started the decking on the 12th and had done the posts as well.

Cutting out the door.



We'd already made the cut inside - the door was framed and sheet rocked over so all we had to do was to cout it out.

An opening to the outside.

Installing the door - it was a very tight fit.

Resting after another long day.

Tuesday, August 9, 2011

Lifting the Glulam into place.


Readying the end posts.

The posts are centered on the footers.

Bolting the post into the concrete retaining wall.

Even with the block and tackle, we had to use the truck to lift the glulam.

Our tripod was almost not tall enough.


Centering the glulam on the post.


Middle posts set.

We added a joist for stability over night.

Monday, August 8, 2011

Setting up the Jin Pole

Jin Pole/tripod lashed together.
Lifting a 35 foot glulam into place was a bit of a challenge.  The carpenter (I'll call call him "X") who I intended to build the deck with, and who had ordered the lumber, backed out ten minutes after he arrived.  He saw that we had stained the rim joists and posts (with water soluble stain.)  He kept saying "Someone's gonna get killed on this job." Based on that, I think he was more concerned with lifting a 35' long 5.25"x9" glulam than he was with fumes from the stain. The delivery driver from the lumber yard claimed the glulam was just about too heavy for their forklift to load.  My calculations say it weighed about 600 pounds. When X arrived and saw the lumber he unloaded the jin poles and then said he was gonna leave -- with his block and tackle! It was obviously necessary for the operation. I called him an asshole  for leaving me in the lurch and  he told me he was going to pummel me. Wisely, Randall remained out of sight. X and I both managed to calm down. I apologized for calling him an asshole and promised to return the block and tackle the following day and he agreed. During the rest of that day, Randall and I lashed together a tripod, moved the glulam into place and set up the block and tackle and finished staining all the joists so we didn't need to mess with stain after building started.

Moving the glue-lam into place.

Ready to go on the morrow.

Sunday, August 7, 2011

Deck lumber arrives and staining begins.

The deck lumber arrived - the large white package contains Meranti Batu decking.

The long wrapped piece was a 35' long glue lam which we had to lift into place.

We started staining boards that would be used for the rim joists right away.

Staining posts.

More staining.